Two Rivers Community School
Two Rivers Community School
Location: Chewko Road, Mareeba
Client: Two Rivers Community School

Stratos Civil continues to make strong progress on the construction of the new Two Rivers Community School, including the associated intersection upgrade and roadworks on Chewko Road.
Since commencing works in February 2026, the project has advanced efficiently despite seasonal wet weather, with key civil infrastructure now completed across the site.
Completed Works
Our team has successfully delivered:
Detailed cut-to-fill earthworks for the building pads and new carpark
Gravity sewer reticulation throughout the school site
Internal stormwater drainage network, including pipes and pits
Culvert crossing installation beneath existing driveways on Chewko Road
Ground improvement works for the new carpark subgrade

Scope of Works
The project encompasses a broad range of civil construction activities, including:
Traffic management for the Chewko Road intersection upgrade
Service location and protection
Erosion and sediment control implementation
Road widening and full pavement rehabilitation of Chewko Road
Detailed earthworks across the school development
Sewer reticulation and stormwater infrastructure
Construction of the new access road and carpark pavements

Delivering Quality Despite Challenging Conditions
Working through North Queensland's wet season requires careful planning, effective site management, and close coordination across all disciplines. Despite these challenges, the project remains on schedule, with the Stratos Civil team maintaining exceptional standards in safety, environmental compliance, traffic management, and construction quality.
We're proud to be delivering the essential civil infrastructure that will support the new Two Rivers Community School and the surrounding community, and we look forward to sharing further project updates as construction continues.