Bew Road Culvert Upgrade
Project progress is taking shape on the Bew Road Culvert Upgrade, with Stratos Civil now in the final stages of construction and pavement works nearing completion.
This project has required careful planning and coordination from day one. With challenging weather conditions, existing services and live traffic to manage, our team implemented a side access track and water diversion to keep works progressing safely and efficiently throughout construction.

Scope of Works:
Traffic management
Service location
Erosion and sediment controls
Construction and removal of side access track
Earthworks cut to fill
Culvert slab and apron/wing walls construction in accordance with TMR standards
Placement of reinforced concrete box culverts
Sub-base and base course pavement
Sealing of finished surface
Signage
Stabilisation of grasses surface

Challenges & Solutions:
Service location and work around existing Telstra service
Construction of culvert slab, aprons, headwall and wingwalls in drainage line
Work performed between inclement weather events
Management of traffic during construction
The Bew Road Culvert Upgrade will provide and improved drainage asset to the Tablelands Region community. All works have been performed in accordance with project standards and in a safe manner.